Delays in construction of the new stadium Panathinaic in Herbal They continue.
Much behind the time will go, as they all show, the completion of the construction of the new Panathinaikos football stadium in the Botanical area, with the new timetable -as it has been submitted by the contractor for the construction of the new football arena, to limit its final project. April 16th 2027.
On the issues of the agenda of the 19th meeting of the Municipal Committee of the Municipality of Athens, which will take place next Tuesday (6/5) at 09:00 via teleconference, to discuss important issues related to the Municipality, as a 39th issue through the “package” of the “Package” of the Board of Directors. He says:
‘Decision on approval:
(a) The extension with a revision of 332 days, that is, until 16.04.2027, without the fault of the contractor, the total deadline of the project “CONSTRUCTION OF PANATHINAIKOS FOOTBALL FOOTBALL”. 150070/19.05.2023 (APA: 955) – AKTOR SA – METKA SA » of AP 118373/02.05.2024 (APA: 9pm6m-A24 and ADAM 24SYMV014762310 2024-05-16), in accordance with article 147 of Law 4412/2016, as in force,
b) of the revised timetable as submitted by the contractor consortium and
(c) the validity of the additional payment clause (premium) in the contractor consortium, provided the project is completed by 3.6 months earlier than the new final deadline of 16.04.2027, that is, earlier than 29.12.2026, in accordance with Article 149 (3) (AP 1111997/02.05.2025) ».
In the contract between the Municipal Authority and the contracting consortium on the afternoon of May 19, 2023, there was a provision for completion of the football stadium within 36 months. That is by the end of May 2026.
During the (informal) foundation ceremony on the work held at the Botanical construction site on the morning of February 3, 2025, it had been said again by official lips of all those involved in the “double regeneration” project in 2026 as a date of completion of the football.
It turned out, however, that this estimate was quite “optimistic”, as the signing of the contract to date have been significant delays in various parts.
With the consortium of the three construction companies, giving a revised timetable to the municipality that includes an extension of the total deadline for the construction of the football stadium by 332 days, compared to the original contract. And a deadline on April 16, 2027, that is, less than two years.
This revised timetable, along with the 332 -day extension, will pass on Tuesday (6/5) from the 9 -member Municipal Committee of the Municipality of Athens, along with the confirmation of “Bonus” to the contractor, if the project is completed by December 29th at the latest.