Eunice: The implementation of two major works in Western Macedonia begins this year

Photo: Istock




Two important works by Eunice Energy Group in Western Macedonia are soon undergoing construction. As highlighted on Thursday (3.4.2025) at the event for the transition of the area in Kozani, the apoliticalization paved the way for new investment In D. Macedonia.

The data center that Eunice will build in Amyntaio with a power of 5 MW is The first in the region and is an investment of EUR 40 million.

By September 2025 the licensing will be completed, and its construction will last 12 – 14 months. There will be 200 employees during the construction, and on a permanent basis 95.

In fact, this is just the beginning, as The company targets 50 megawatts from data centers. “We have chosen Western Macedonia to exploit network infrastructure, huge photovoltaic production, combination with energy storage and the ideal temperature it offers for data centers,” Eunice said.

At the same time, there was also talk of the great energy storage project with batteries, Bess Ptolemais, a budget of € 300 million. The construction is expected to begin at the end of the year, which will last 20 – 22 months, and 100 permanent workers will be employed.