In the modernization, reinforcement and extension of its electricity distribution network Thessaloniki proceeds the HEDNO.
All this after the Bora bad weather that hit the Thessaloniki area in December 2024 and caused significant problems. Now, HEDNO is making an effort to shield the network against corresponding phenomena.
According to a letter submitted to the House, the plan includes the following:
- Construction of underground/upgrading projects of the network totaling 140km and budget of more than EUR 14 million with completion in late 2025.
- Manufacture of modernization projects of the airspace, with a total length of 30km and a budget of € 1 million with completion at the end of this year.
- Current upgrading of 940 points of regional remotelying and protective intercourse, indicative error transit and installation of additional air and underground network that enhance the tele-review and allow faster isolation/re-feeding in cases of unlocked holidays.
- Accelerate the rate of replacement of cash with smart meters. So far in the IP 65,000 smart meters have been installed in Thessaloniki.
- Completion of firefighting projects near the network.
- Implementation of the planned inspection, maintenance, deforestation per year at all intended points.
The above moves, according to HEDNO, significantly upgrade the capabilities of the network and shield it against the adverse effects of climate change and extreme natural phenomena.
Indeed, HEDNO points out that there is already a significant decline in unlawful electricity holidays as a result of the actions.